Electrical installation works at the steelworks construction

In 2015, 9 projects in the field of electrical installation were commenced at the construction of a new copper acquisition block at the KGHM steelworks in Głogów. Within the scope of the company’s work, all 9 projects were:
 

kwadrat assembly of cable routes,
kwadrat laying routes of power and control cables,
kwadrat performance of all required electrical measurements,
kwadrat connection and checking its’ correctness,
kwadrat start-up assistance

Scope of work:
kwadrat 9 projects – electrical installation works

The team implementing the projects numbered about 70 people. Works on this type of object are non-standard works, carried out at high altitudes. Power cables have been routed in previously prepared cable routes at a height of up to 60 m from ground level. It took one year and was successfully completed on time.

OTHER INTERESTING

PPM300 Liquid Cooling System in Comsys Active Filters
PPM300 Liquid Cooling System in Comsys Active Filters View more
ANIRO at the conference in Nadleśnictwo Toruń: Energy transformation and new energy storage technologies.
ANIRO at the conference in Nadleśnictwo Toruń: Energy transformation and new energy storage technologies. View more
Innovative robotic solutions for the Wood Industry with ANIRO cobots.
Innovative robotic solutions for the Wood Industry with ANIRO cobots. View more